Downtown Reconstruction Project

2019 Downtown Reconstruction Project Closure Map

Overview

The Downtown Chaska Reconstruction continues on the east side of Hwy 41. Portions of Walnut St., E 4th St., Oak St., and E 5th St. will be impacted. Crews will be upgrading the utility services as well as the street, sidewalk and boulevard. The construction of the road and utilities will require various road closures and detours throughout the summer between June and October.

Timeline

CenterPoint Energy is upgrading and relocating their gas facilities in the project area. 

Stage 1

  • Begins early July
  • 4th St closed between Walnut St and Ash St
  • Oak St closed between 4th St and 3rd St

Stage 2 

  • Expected to begin in August, weather and schedule permitting
  • Closures impacts: 
    • Oak St between 5th St and 4th St 
    • Walnut St between 4th St and 3rd St

Current Traffic Impacts

Week of 6.17.19: CenterPoint continues utility improvement work. There are no expected impacts to traffic.

Resources

View the Downtown Reconstruction Project Map